A Member has reported a serious crane wire failure. A night-time recovery of a work-class ROV (weight 4.75 Te) was taking place onto a Class 2 DP survey vessel using the ship’s 5 Te crane.
What happened?
Weather conditions were fair with an estimated 0.5 m significant wave height on top of a 1.5m swell.
During recovery of the ROV, the supervisor could hear the crane hydraulics bypassing the pressure relief valves – indicating an overload.
On trying to lift again, the crane wire parted and the ROV was released to sea.
What were the causes?
The company’s investigation revealed:
- scuffing/gouging of the spelter socket
- recent and historical damage on the inside face of the swivel sheave cheek plates – indicative of a wire scraping along the plates
- the cheek plates had been distorted outwards by approximately 30 mm
- damage to the outer face of the sheave wheel
- crushing and mechanical damage to the broken ends of the crane wire.
The company has concluded that the crane wire had been over-recovered in the past, to the extent where the conical end of the spelter socket had forced itself between the sheave assembly cheek plates, wedging them apart by circa 30 mm. This, in turn, allowed the wire rope to come off the sheave and jam between the wheel and the cheek plates, causing crushing damage to the wire. The additional impact load on the already damaged wire during the recovery of the ROV through the splash zone ultimately led to the failure of the wire.
The root causes of the failure were noted as:
- inadequate crane inspection ‘routine’s
- no action had been taken when the existing damage had previously been noted
- the crane had been previously modified without recourse to a management-of-change procedure or consultation with the manufacturer
- there was no limit switch fitted to restrict the spelter socket from entering between the cheek plates.
Actions
The company has implemented the following corrective actions:
- Checklists have been modified to include visual inspections of the crane wire and sheave assembly and communication of findings to management and crane manufacturer as appropriate.
- The importance of the management of change procedure has been re-emphasised.
- Risk assessment reports have been reviewed and updated as required, highlighting the risks of damaged crane parts.
IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of the entire offshore industry.
The effectiveness of the IMCA Safety Flash system depends on the industry sharing information and so avoiding repeat incidents. Incidents are classified according to IOGP's Life Saving Rules.
All information is anonymised or sanitised, as appropriate, and warnings for graphic content included where possible.
IMCA makes every effort to ensure both the accuracy and reliability of the information shared, but is not be liable for any guidance and/or recommendation and/or statement herein contained.
The information contained in this document does not fulfil or replace any individual's or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.
Share your safety incidents with IMCA online. Sign-up to receive Safety Flashes straight to your email.