Solitons – Be mindful
- DP Event
- Published on 13 April 2022
- Generated on 22 February 2025
- DPE 01/22
- 2 minute read
Observation
A number of our Members have submitted DP Event Reports which highlighted the phenomena of a sudden loss of position due to Solitons.
Solitons are large amplitude, often highly nonlinear, internal waves. They are responsible for complex vertical profiles of rapidly fluctuating ocean currents. These current profiles and their effects are not fully quantified and there is very little supporting data.
Solitons are difficult to predict. IMCA recommends that the bridge crew research their geographic area of operation and be mindful that the vessel is susceptible to sudden increase of sea currents.
The figure above shows how a Soliton can be shown on radar.
These waves can travel at two to four knots. This, along with the physical effects of the waves, can cause a sudden loss of position followed by severe ramp up of thrusters and generators.
In the case of DP vessels, there is insufficient time for the vessel mathematical model to update. The vessel may remain unstable in terms of position and heading for some time after, overshooting and hunting the set point values. At the same time, unreliable results will be obtained from subsea position references. Both taut wire and HPR systems will be degraded due to velocity of surface and subsea water with additional noise and aeration from thrusters.
Latest DP incidents
-
Thorough preparation is key
With 4 of 8 diesel generators running and connected to a closed ring bus, and 7 of the 8 thrusters selected to DP, a DP equipment class 3 MODU was set up in Green mode whilst on standby.
DPE 03/24
5 November 2024
Incident
-
There – but not really there
This DP event occurred on a DP equipment class two supply vessel whilst carrying out cargo operations on the starboard side alongside the asset and working at the lee side in the drift-off position.
DPE 03/24
5 November 2024
Incident
-
Equipment Class 3, even if you operate as 'Class 2'
This case study examines a DP incident on an equipment class 3 multi-purpose vessel while operating in good conditions.
DPE 03/24
5 November 2024
Incident
-
Line of sight
This case study covers events onboard a DP equipment class 2 vessel whilst holding position in a turbine field, with three position reference systems selected into DP – DGPS, HPR and Fanbeam.
DPE 03/24
5 November 2024
Incident
-
DP Drill Scenario
DP emergency drill scenarios are included to assist DP vessel management, DPOs / Engineers, and ETOs in conducting DP drills onboard.
DPE 03/24
5 November 2024
Incident
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.