Maintenance – Not a good idea during DP operations
- DP Event
- Published on 11 August 2022
- Generated on 29 September 2026
- DPE 02/22
- 3 minute read
Incident
Jump to:
This event occurred as a result of the decision to replace a critical switchboard component while remaining on DP.
Overview
An Offshore Supply Vessel (OSV) was conducting an ROV survey in open water, the bustie was closed creating a single power grid, as per Task Appropriate Mode (TAM) configuration.
The OSV was in Auto DP using two Position Reference Systems (PRS’) selected into DP Control all with automatic weighting, the PRS’ selected were:
- x2 DGNSS
The power plant was set up as below with two generators (G2 and G3) connected.

During routine maintenance on Tx1 the 480Vac bustie was closed, and the two feeder breakers for Tx1 were opened to allow Tx1 to be isolated.
G2 and G3 were connected to the 690Vac switchboard.
Upon completion of the maintenance it was noted that the 690Vac feeder to Tx1 would not close.
Troubleshooting determined that a Port 690Vac switchboard ‘REF’ protection relay was faulty and needed to be exchanged.
The vessel continued conducting DP operations.
It was decided to exchange the ‘REF’ relay. After remounting the replacement relay and in the process of terminating the new relay, an unknown live wire inadvertently contacted a surface and grounded. This grounding caused the remaining 690Vac circuit breakers on the Port bus to trip and open, since they were connected via “daisy chain” configuration by design for protection purposes. This then caused the bus tie to open as per design in order to protect the Starboard power bus. Port Azi and BT1 failed as a result.
The bus tie opened upon sensing low voltage on the Port bus. No loss of Position was experienced.
What can be concluded?
- That the vessel was configured in such a way that a single failure would exceed the WCFDI.
- The event occurred as a result of the decision to replace a critical switchboard component while remaining on DP.
Additional comments
- This was recorded as a Human Factor triggered event.
- The power system was configured as per a TAM presumably with the knowledge and understanding of all stakeholders that the vessel could lose position. The TAM may have been agreed, but it’s unlikely that the increased risk caused by conducting maintenance would have been.
- It was not clear if an ASOG was in place and if it was being followed. While operating in TAM will allow for a lesser fault tolerance, the system integrity has been further compounded by vessel maintenance activities.
- It is not clear whether the closed bus configuration had been fully analysed in the FMEA. If so, then the analysis appears to have missed the failure mode associated with common power supply. If not considered within the FMEA then the decision to operate closed bus had additional risk of unknown failures.
- The event highlights the risk of undertaking maintenance / repair of components critical to the integrity of the DP system (in this case the main switchboard). It also highlights the importance of management of change procedures.
- This case study highlights the dangers of working on a live switchboard and also highlights the risks of not ensuring appropriate isolation of electrical components. This event could easily have resulted in personal injury.
Latest DP incidents
-
Know your equipment, or at least where to find the answers
During an update in the Follow Target Mode, the crew noticed an anomaly with joystick control.
DPE 02/26
1 September 2026
Observation
-
New equipment, unexpected consequences
During the operation, a loss of DGNSS correction signals was experienced across multiple vessel DGNSS units.
DPE 02/26
1 September 2026
Incident
-
A chain of small failures leads to a major consequence
While conducting cargo operations on DP a vessel experienced a partial blackout caused by an unexpected shutdown of generator 3
DPE 02/26
1 September 2026
Incident
-
Holding position, losing references
While approaching a turret-moored, weather-vaning offshore installation (FPSO), in preparation for cargo operations, a DP equipment class 2 vessel experienced significant rolling of up to 15–20° due to a long-period swell close to the vessel’s natural roll period, resulting in a resonance effect
DPE 02/26
1 September 2026
Observation
-
DP drill scenario – Loss of seawater cooling pump redundancy
Exercise scenario – Loss of seawater cooling pump redundancy
DPE 02/26
1 September 2026
Drill Scenario
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.